6/1/07 - Sheetrock is finished.
6/8/07 - Sheetrock mud and taped along with the textured finish was
completed today.
6/9/07 - The floors are being stained by local company Turner Coastal Concrete.
Contact Shannon at 813*541*9167 for more information. They specialize
in interior and exterior concrete finishes. See pictures of our floors.
6/11/07 - The ceilings are being painted with a material called dryfall. It
is a paint and insulation product that will help keep our energy costs
down.
6/14/07 - Just when things are looking great, the painting is almost complete
the painters fall through the office ceiling.
6/15/07 - Sheetrock repairs. Rubber flooring is delivered. Everything must
be complete by the 19th as our equipment is being delivered.
6/18/07 - One of our project supervisors walked off the job. The floor installation
crew is on-site and we are still moving forward.
6/19/07 - The rubber floors take our flooring crew 5 hours to clean. They have worked
straight through the night without stopping knowing that the equipment
is being delivered. It becomes clear why the supervisor walked off the job.
Equipment is delivered but just left on-site, it is not installed.
6/20/07 - Tanning beds and vending machines are delivered. Equipment is scheduled
for installation on Friday.
6/21/07 - Mirrors are hung, security installed, touch up paint complete. Fast Signs of Brandon
hangs all door and wall vinyl. We have electricity and phones.
6/25/07 - Now for inspections....
6/28/07 - We have passed all inspections, the Building final, even the Fire Marshall
all of them save one....
The plumbing inspection was failed due to the ADA seat requirement
which we have on-site but are having difficulties installing due to the
ceramic tile. This will delay us, as inspectors do not work on Fridays.
Therefore we are forced to wait until Monday for that final. We anticipate
holding the Member's Open House Monday July 2nd 6 pm - till. We will
open to the Public on July 3rd.